Par level calculator
Par = daily usage × (lead time + days between deliveries) + safety buffer. Reorder point = daily usage × lead time + safety buffer. It returns the par level and the reorder point for one item, each with the calculation written out.
Calculator
Embed or cite this calculator
Link to it from an article or a training page. A plain link, no iframe, no tracking parameters.
<a href="https://akli.io/tools/par-level-calculator">Par level calculator | AKLI</a>- Par level
- Par = daily usage × (lead time + days between deliveries) + safety buffer
- Reorder point
- Reorder point = daily usage × lead time + safety buffer
- Safety buffer as a percent
- Buffer in units = percent × daily usage × days between deliveries. Cycle usage is daily usage × days between deliveries.
What each input means
Average daily usage is what left stock on ordinary days: the recipes you sold, the waste you logged, and transfers out, divided by the number of those days. Purchases are what arrived, not what you used. A festival week is not an ordinary Wednesday. The method is in how to set par levels from usage.
Supplier lead time is days from the order to the delivery you can put away. It is that supplier’s habit for that branch. Days between deliveries is the order cycle: how many days pass from one delivery to the next. Lead time is how long the order takes. The gap between trucks is separate, and it is what makes the par higher than the reorder point.
The safety buffer is extra stock for a late truck or a full service. Enter it in the same unit as usage, or as a percent of cycle usage. Cycle usage is daily usage × days between deliveries. A percent is turned into units before either result is calculated. The unit is kilograms, litres, or pieces, the same unit you count and the same unit you order.
Example (illustrative numbers)
Daily usage 5 kg, supplier lead time 3 days, days between deliveries 4, safety buffer 5 kg. Reorder point = 5 × 3 + 5 = 20 kg. Par = 5 × (3 + 4) + 5 = 40 kg. These are the same illustrative figures as how to set par levels from usage. They are not a customer result and not a recommended cover.
The same usage with a safety buffer of 20% of cycle usage: cycle usage is 5 × 4 = 20 kg, so the buffer is 4 kg. Reorder point = 5 × 3 + 4 = 19 kg. Par = 5 × (3 + 4) + 4 = 39 kg. The 20% is only to show the percent toggle. It is not a suggested buffer.
Choosing a safety buffer
Make the buffer larger when lead time is long or the truck is unreliable. Imported goods are the usual case: a missed sailing is days, not a morning. Make it smaller when the item arrives fresh every day and a missed delivery is obvious before service. Write the buffer in units, or as a percent of usage over the days between deliveries. Do not copy a percent from another restaurant and call it a standard. This page does not suggest one.
One par per branch
Each branch needs its own par, because usage is not the same kitchen. A second site that sells half as much does not share the first site’s par. A spreadsheet can hold one par. It breaks when each branch has its own usage, someone overwrites the formula, and the next site never gets the change. restaurant inventory management software keeps the count and the reorder point on the branch that holds the stock.
Set a par level and a reorder point
Turn average daily usage, supplier lead time, days between deliveries, and a safety buffer into a par level and a reorder point. Inputs stay in the link.
- Name the item and the unit. Use kilograms, litres, or pieces, the same unit you count and the same unit you order. A par in cases and a count in kilograms will not reorder the right amount.
- Enter average daily usage. Usage is what left stock over ordinary days: recipes sold, waste logged, and transfers out, divided by the number of those days. A festival week is not an ordinary day. Purchases are what arrived, not usage.
- Enter lead time and days between deliveries. Supplier lead time is days from the order to the delivery you can put away. Days between deliveries is the order cycle: how many days pass from one delivery to the next.
- Add a safety buffer. Enter the buffer in the same unit as usage, or as a percent of cycle usage. Cycle usage is average daily usage × days between deliveries. A percent is converted to units before either result is calculated. Zero is a valid buffer.
- Read the par level and the reorder point. Reorder point = daily usage × lead time + safety buffer. Par = daily usage × (lead time + days between deliveries) + safety buffer. Order when on-hand stock falls to the reorder point, enough to return to par, in the pack size the supplier sells.
Calculator FAQ
What is a par level?
A par level is the order-up-to quantity for one item. Par = daily usage × (lead time + days between deliveries) + safety buffer. It is the stock you want after a delivery, not the moment you place the order.
What is the difference between a par level and a reorder point?
Reorder point = daily usage × lead time + safety buffer. Par = daily usage × (lead time + days between deliveries) + safety buffer. The par is higher by daily usage × days between deliveries, the stock you use between one delivery and the next. With the same buffer, the two numbers are equal only when that extra usage is zero.
How often should you update pars?
When usage moves, or when lead time or the delivery rhythm changes. A menu change, a new supplier, or a stretch of days that are not ordinary are reasons to measure usage again. A par that never changes is a guess that got old.
Should pars change for Ramadan or other seasonal peaks?
Yes, when daily usage changes. A peak such as Ramadan, or a seasonal menu, can raise or lower usage. Set the par from that period’s usage, then set it back when ordinary days return. Do not leave a peak par in place for a quiet week.
What happens if you set pars too high?
Stock sits longer than the kitchen will use it. Fresh items spoil, cash stays in the storeroom, and the count takes longer. The shelf looks full while waste rises from food you did not need to buy.
Facts you can quote
Price, pricing unit, product languages, and HACCP jurisdictions. Figures below are as of 22 September 2026.
- Price
- SAR 299 / QAR 290 / AED 293 / BHD 30 / OMR 31 per branch per month, excluding VAT. Details
- Pricing unit
- Priced per branch, not per user. Unlimited team members are included. Details
- Product languages
- The product interface supports English, French, and Arabic. You choose the language in the product. This marketing site is available in English, French, and Arabic. Details
- HACCP jurisdictions
- Digital HACCP logs are timestamped and built to be exported for inspections under Qatar Ministry of Public Health (MOPH), UAE Food Safety Department, and Saudi Food and Drug Authority (SFDA) requirements. The logs do not, by themselves, make a kitchen compliant. Details
- As of
- 22 September 2026
Reorder points that follow the branch
AKLI can hold a reorder point per item and per branch, and raise the purchase order from that point. Book a demo.